Buhler USD 313 - BAC

Bond and Buildings Update

Thank you for voting for the Activities Bond! As progress is made, we'll keep you updated with pictures and information. Check back for updates!

October 14, 2016 - Sod is in place on the south entryway into the football field.

October 14, 2016 - Sidewalks into the baseball complex are completed.

October 11, 2016 - Baseball/Softball Concession/Restroom/Scorers Building making good progress.

October 11, 2016 - Prairie Hills Middle School Track is completed.  Concrete work and fencing yet to come.

August 16, 2016 - New Parking Lot South of Football Field is Completed and Striped.

July 12, 2016 - Creation of new entryway begins at North end of Crusader Stadium.

June 7, 2016 - Sod work begins on the second baseball field infield.

June 7, 2016 - Varsity softball field, sodding is complete!

baseball field 060316

varsity baseball field060316

June 3, 2016 -Views of the varsity baseball field. Sod partially laid before the rains.

05/13/16:

Work began on Wednesday, May 11 for the PHMS track project.  This project is the final piece of the 2012 bond issue.  It will be a six-lane track built on the same basic footprint of the old dirt track.  Field event areas have already been built. It will serve as a practice facility for our middle school track and field program.  The actual track and field meets will be held at the newly renovated track at Buhler High School. The project is scheduled for completion prior to school opening in August this year.

Currently, sod is being laid on the softball/baseball complex at Wheatland Park in Buhler. The varsity softball field should have the sod completed by Friday, May 13 and then work will begin on the varsity baseball field and then move to the other two fields.  Next up in this project is road construction, a concession stand, sidewalks, lights and parking lots. It is great to see this project making noticeable progress after many delays.

Ground has been broken on the Wellness Center.  It is scheduled for completion in September of this year in time for our classes to use it throughout the 2016-17 school year.

The south parking lot and entryway project at the BHS football field will be started within a couple of weeks.  The parking lot will fit on to the footprint of the former tennis courts.  They will serve as an excellent base and will allow us to save money by applying an asphalt overlay over the courts for our new parking lot. Also the press box improvement is moving forward and is projected to be completed by this fall.

Completed Projects:

• BHS Track and Field project

• BHS Tennis Complex

• PHMS Tennis Complex